Home >
Texas Highwayman Pages > San Antonio Freeway
System > 281/410 Interchange
Work began on July 6th, 2005, on the $154.7
million project to build a fully-directional interchange at US 281 and
Loop 410 next to San Antonio International Airport. When completed
in 2008, a massive four-level interchange will facilitate direct
connections between the two freeways, replacing the overburdened surface
street and access road connections currently used by about 100,000
motorists daily. The project was
originally scheduled to be built in five phases over ten years. However, new funding mechanisms from the
legislature allowed the projects to be combined, saving a considerable amount of
time and money.
Initially, the new consolidated project, which will
build the entire interchange at once, was projected to take five years
to build, but the contractor's bid was for just over three years! Work continues 24 hours a day, seven days a week.
In addition to the actual
interchange ramps, this project is also adding additional lanes on Loop
410 and US 281, reconfiguring several surface streets, access roads and
intersections, and relocating several exit and entrance ramps along both
freeways. In totality, this project will dramatically reshape
traffic patterns in North-Central San Antonio.
This is the largest single highway
construction project ever awarded in San Antonio and is part of the overall
Loop 410 Expansion
Project.
In late 2005, a contest was
held to name this interchange. "The Web" was the name selected.
Details
The map below shows the overall
scope of the project. As you can see, it extends well beyond the
actual 281/410 crossing. Click on any section of the map for a
close-up engineering plan of that area. Each of the images is over 100KB and
will open in a new browser window.

Click on a
map segment above to see detailed plans for that area.
(Engineering
plans courtesy of TxDOT)
This will be a four-level
interchange:
- Level 1 (bottom): Loop
410 mainlanes and access roads
- Level 2: US 281 mainlanes
- Level
3: Ramps from
US 281 to Loop 410
- Level
4: Ramps from
Loop 410 to US 281
The project will use:
- 60,000 cubic yards of
concrete (enough to cover 30 football fields, 1 foot deep)
- 322,000 tons of hot mix
asphalt (enough to pave 975 football fields)
- 11 million pounds of steel
beams (enough to build over 3,200 cars)
- 119,695 linear feet of
concrete beams, which would stretch 23 miles if placed end-to-end.
The beams for the largest bridge span are 195 feet long and weigh in
excess of 45 tons each.
(Stats courtesy of TxDOT.)
Status
Major construction began on July 6th,
2005. The
project is about 86% complete (January 2007) and should be done in
the 3rd quarter of 2008.
Click here for construction photos

Estimated ramp completion dates:
| |
|
281 southbound to
410 eastbound: |
2Q 2008 |
| |
|
281 southbound to
410 westbound: |
June 18, 2007
(open!) |
| |
|
410 eastbound to
281 northbound: |
January 27, 2008
(open!) |
| |
|
410 eastbound to
281 southbound: |
February 18, 2008
(open!) |
| |
|
281 northbound to
410 eastbound: |
2Q 2008 |
| |
|
281 northbound to
410 westbound: |
December 22, 2007
(open!) |
| |
|
410 westbound to
281 northbound: |
April 4, 2008
(open!) |
| |
|
410 westbound to
281 southbound: |
April 4, 2008
(open!) |
The Express-News has a jazzy Flash animation of the ramp opening sequence
here.
Here are the completion dates
for other major elements of this project:
- US 281 widening to
eight lanes from Hildebrand to Jones-Maltsberger:
Completed
- Loop 410 EB access
road overpass at Wetmore: Completed
- New SB 281 exit to
Jones-Maltsberger (Quarry): Completed
- US 281 widening to
eight lanes from Jones-Maltsberger to Nakoma: 1Q 2008
- Loop 410 widening to
10 lanes: 4Q 2008
Current long-term closures
- EB Loop 410 exit to
Jones-Maltsberger: Closed permanently-- use San Pedro exit.
- EB Loop 410 exit to
Broadway/Wetmore: Closed until mid 2008-- use Airport Blvd.
exit.
Project history
Any motorist who drives any
appreciable amount
of time on San Antonio's freeway system will eventually come upon the
410/281 non-interchange. This intersection is often cited
as the only place in Texas where two major urban freeways cross without
direct connections between them. About 300,000 vehicles a day
travel through the area and traffic frequently queues on Airport Blvd.
and the westbound 410 access road as drivers negotiate their way between
the freeways. Only one of the turns requires no interaction with a
traffic signal. All of the remaining directions require motorists
to pass through at least one signalized intersection. While many
people simply blame this traffic nightmare on poor planning, the real
story is not so simple.
When planning for the North
Expressway (US 281) was going on in the late '50s and early '60s, there
were heated debates over the route that the new freeway should take.
After evaluating several routes including San Pedro and Broadway, the
route skirting Brackenridge Park, slipping between the Zoo and Alamo
Stadium, and continuing north over the Olmos Basin was chosen.
This route also caused great protest, but construction on the northern
and southern thirds of the freeway began anyway. Opponents of the
route got a federal court order halting construction on the grounds that
the freeway violated a new federal rule disallowing freeways from
crossing parklands and saying the freeway would cause great disturbance
to the animals at the zoo. Meanwhile, the City, which had been
charged with obtaining the right-of-way for the project, was in the
midst of condemning land for a planned 410/281 interchange.
The injunction stopping the freeway construction caused the City,
uncertain as to the future of the project, to stop dead in its tracks as
well. The court battle dragged on for several years. Before
long, with development booming along the Loop, owners of the condemned
property demanded that the City either buy the land or release it from
condemnation. At that time, the freeway looked doomed, so the City
lifted the condemnation. New buildings sprang-up at the
interchange site almost overnight. When the freeway eventually did
come through several years later, the cost of the land was prohibitively
expensive and the interchange was scrapped. (For more information on the
history of 281, see my
US
281 North page.
For a diagram of the originally proposed interchange, see the
historical maps page.)
Until the mid '80s, traffic
volumes were low enough to allow relatively easy access between the
freeways using access roads and adjacent surface streets. However,
by the early 1990s, traffic volumes began to severely overload this arrangement. To fix the
problem, TxDOT began design work on a four-level, $124.5 million interchange.
Several preparatory projects in the vicinity were undertaken in the mid and late
'90s. These projects included the widening 410 between McCullough
and Jones-Maltsberger and the placement of most of the future ramp pylon
pedestals along that stretch. The US 281 overpasses over Loop 410
were also rebuilt and a couple of strategic turnarounds added. Additionally, a ramp from northbound US 281
directly
into the airport terminal area was built. This
ramp was proposed and funded separately by the airport and the FAA and was inserted into the
overall interchange construction plan by TxDOT.
After several years of uncertainty
over funding, the state finally funded the entire project in late 2004.
In late 2005, a contest was
held to name this interchange. "The Web" was the name selected.
The first ramp to be
completed, from
281 SB to 410 WB, opened to traffic on the afternoon of June 18th, 2007, marking
the beginning of the end for this storied non-interchange.
Additional information
|