FREEWAY |
LOCATION & DESCRIPTION OF WORK |
 |
- CAMP BULLIS to
KENDALL COUNTY LINE
Widen freeway from four to six or eight lanes
- LOOP 410 (East) to
GUADALUPE COUNTY LINE
Widen freeway from four to eight lanes
- CAMP BULLIS to FM
3351
Install TransGuide equipment
- ROLAND to LOOP 1604
Install TransGuide equipment
- At LOOP 410 (East)
Replace parts of existing cloverleaf interchange with new
multi-level directional interchange
|
 |
- I-37 to FM 3009
Add four managed toll express lanes
- At LOOP 410 (North)
Replace existing interchange with new multi-level
directional interchange
- US 90 to SW MILITARY
Widen freeway from six to eight lanes
- SW MILITARY to LOOP
410 (South)
Widen freeway from four to eight lanes
- LOOP 410 (South) to
ATASCOSA COUNTY LINE
Widen freeway from four to six lanes
- SOUTHCROSS to FISCHER
Install TransGuide equipment
|
 |
- LOOP 410 to ATASCOSA
COUNTY LINE
Widen freeway from four to six lanes
|
 |
- At LOOP 410
Replace existing cloverleaf interchange with new multi-level
directional interchange
- At LOOP 1604
Build new multi-level interchange
- At SP 371
Build new interchange
- LOOP 410 to SH 211
Widen freeway from four to six lanes
|
 |
- At LOOP 410
Build new interchange
- At LOOP 1604
Build new interchange
- ENTIRE ROUTE
Install TransGuide equipment
|
 |
- BORGFELD to BLANCO
COUNTY LINE
Upgrade to six lane freeway/tollway
- NAKOMA to EVANS
Install TransGuide equipment
|

 |
- US 90 to CUPPLES
Widen freeway from four to six lanes
- At US 90
Build new interchange
- CUPPLES to SH 16
(South)
Build new parkway (Kelly Parkway)
|
 |
- US 90 (West) to
CULEBRA
Widen freeway from six to eight lanes
- At US 90 (West)
Replace existing cloverleaf interchange with new multi-level
directional interchange
- US 90 to I-35 (South)
Widen freeway from four to six or eight lanes
- At SH 151
Build multi-level directional interchange
- At I-35 (South)
Replace existing cloverleaf interchange with new multi-level
directional interchange
- I-10 (East) to I-35
(North)
Widen freeway from four to six lanes
- At I-10 (East)
Replace existing cloverleaf interchange with new multi-level
directional interchange
- CULEBRA to I-35
(North) (southern arc)
Install TransGuide equipment
|
 |
- US 90 (West) to FM 78
(southern arc)
Upgrade to four lane divided highway
- At US 90 (West)
Build new multi-level interchange
- At I-10 (East)
Build new multi-level interchange
- BANDERA to US 90
(West)
Install TransGuide equipment
- TRADESMAN to I-10
(East)
Install TransGuide equipment
|
 |
- JONES-MALTSBERGER to WEST
AVE.
Buildf new parkway
- ENTIRE ROUTE
Install TransGuide equipment
|