Home >
Texas Highwayman Pages > San Antonio Freeway
System > Loop 410 > Expansion Project
While recent construction has
resulted in a substantial drop in traffic, prior to 2003, Loop 410 North
was the most heavily traveled roadway in South Texas, carrying around
200,000 vehicles per day along its northern arc. Most of the
corridor is only six lanes, resulting in significant congestion during
most of the day.
To improve mobility in the Loop 410 corridor, TxDOT has now started the
largest highway expansion program in San Antonio's history, a
seven-year, $483 million program to widen Loop 410 to 10 lanes from
Culebra to I-35 North. In addition, new four-level interchanges at
I-10 and US 281 are included in this program as are new interchanges at
San Pedro and Bandera Rd.
Overview
Not including the 1-10 and US 281
interchanges, there are eight projects to widen the Loop between I-35
and Culebra. Four projects have now been completed.
Loop 410
construction phasing schematic
Scroll to see the entire project
The section between Fredericksburg
Rd. and Cherry Ridge is included in the
Northwest Interchange
project. The section between McCullough and Nacogdoches Rd. is
included in the US 281/Loop 410 interchange
project.
Status (as of
January 2007)
- Culebra to Ingram: This project is
77% complete. Projected completion is the 3rd quarter of 2008.
- Ingram to Callaghan
(Bandera Interchange):
See the special
Bandera/410 Interchange project page.
- Callaghan to
Fredericksburg Rd: Completed in early 2004.
- I-10/Loop 410 interchange:
See the special
Northwest Interchange project page.
- Cherry Ridge to West Ave:
Completed in 1997. Although the pavement width is for 10
lanes, only eight lanes are striped due to the bottleneck at the
I-10/Loop 410 interchange, which limits the number of approach lanes
from the east, and the existing six-lane bottleneck at Blanco, which
limits the number of approach lanes from the west. When the
projects on either side of this section are completed, the
additional lane will be striped and opened to traffic.
- Jackson-Keller to
Honeysuckle: Completed in late 2003. See note above about
additional lane.
- Honeysuckle to Blanco Rd:
Completed in mid 2004. See note above about additional lane.
- Blanco Rd to McCullough
(San Pedro Interchange): This project is
98% complete. Projected completion is the 2nd quarter of 2008.
- US 281/Loop 410
interchange: See the special
US 281/Loop
410 interchange project page.
- Nacogdoches to Austin
Hwy: This
project is 29% complete. Projected completion is the 2nd
quarter of 2010.
Current long-term closures
- Loop 410
westbound exit to Evers:
Relocated to Summit Pkwy.
exit.
- I-10/Loop 410
interchange: See the special
Northwest Interchange project
page.
- Loop 410 eastbound
exit to Jones-Maltsberger: Permanently closed; use San Pedro
exit instead.
- Loop 410 westbound
entrance from Broadway: Closed until late February.
- Loop 410 eastbound
exit to Wetmore/Broadway: Closed until March; use Airport Blvd.
exit instead.
Project history
A Major Investment Study (MIS) of
the Loop 410 corridor from I-35 North to Culebra conducted in 1996 for
the Metropolitan Planning Organization (MPO) recommended expansion of
the freeway to 10 lanes from Austin Hwy. to Ingram. There
initially was some discussion on double-decking the lanes, but that was
eventually dropped.
TxDOT had a website called
"410forSA.org" that had details on the Loop 410 projects, but that site
disappeared inexplicably in mid 2004.
|