I-10/I-410 Interchange
San Antonio Area Freeway System
Northwest (Crossroads) Interchange Construction

 

Home > Texas Highwayman Pages > San Antonio Freeway System > Northwest Interchange

TxDOT is in the midst of a six-year, $134 million project to replace the outdated and overburdened two-level modified cloverleaf interchange with a four-level directional (or "stack") interchange.  When completed in mid 2007, the new interchange will have the capacity to handle 600,000 vehicles per day and dramatically improve traffic on both Loop 410 and I-10 in the northwestern part of the city.  The interchange project will also remove the left-hand exits and entrances, add additional main lanes on Loop 410 and I-10, and provide continuous access roads on both freeways through the interchange.

This project is part of the overall Loop 410 Expansion Project.


Details

The diagram below shows the interchange design and phasing.  If you'd like to see the full-sized diagram (334KB), click here.  For renderings of what the completed interchange will look like, click here.

NW Interchange diagram

Cherry Ridge is at upper left; Fredericksburg is at lower right; Crossroads is at upper right; Callaghan is at lower left. The building within the ramps to the right of the center of the interchange is the TransGuide operations center.
(Courtesy: TxDOT)

This will be a four-level interchange:

  • Level 1 (bottom): Loop 410 mainlanes and continuous pass-through access roads (this level will be about 30 feet below the current ground level)
  • Level 2: I-10 mainlanes and continuous pass-through access roads
  • Level 3: Ramps from Loop 410 to I-10
  • Level 4: Ramps from I-10 to Loop 410 (this level will be about 100 feet above Level 1)

The Loop 410 and I-10 access roads will not intersect at-grade.

No additional right-of-way was required for this project.


Status

Phase 1 started on January 3, 2000 and was completed in early 2003.  The first of the new elevated ramps, from I-10 inbound to Loop 410 east and westbound, opened to traffic on June 7th, 2002.  The ramp from eastbound 410 to outbound I-10 opened on November 12, 2002.

Phase 2 began in Fall 2003 and is about 97% complete (March 2007).  Construction is expected to be completed in the first quarter of 2008.  The ramp from westbound Loop 410 to I-10 westbound opened on May 7th, 2005.  The ramps from both directions of Loop 410 to inbound I-10 opened on December 17th, 2005.  The ramps from outbound I-10 to both directions of Loop 410 opened on November 8th, 2007.

Click here to see construction photos.


Current long-term closures

  • Fredericksburg entrance to eastbound Loop 410: Closed for the duration of the entire interchange project.  A new entrance to Loop 410 eastbound will built late in Phase 2.
    Recommended detour: Follow the access road around to Crossroads.  Take the turnaround under I-10 and enter I-10 westbound.  Then exit onto Loop 410 eastbound.
     
  • Westbound (outbound) I-10 exit to Callaghan: Closed for the duration of the entire interchange project.  A new exit will be built late in Phase 2.
    Recommended detour: Exit at Medical and turnaround.

Project history

Originally built in the late '50s and early '60s, this interchange carries over 350,000 vehicles daily and is the most congested in the San Antonio area.  It is well beyond its design life and is constantly overloaded.

To solve the chronic congestion problems, TxDOT proposed a five-level interchange in the late '80s as the preferred solution.  The final proposal, however, was the four-level interchange now under construction.  The four-level design was chosen over the previous plan for several reasons:

  • Savings of ~$20 million in construction costs.
  • Reduction of construction time by approximately three years.
  • One less construction project.

The extra level would have been for the I-10 and Loop 410 access roads to intersect.  The current design places the access roads at the same level as their parent freeway and therefore they will not intersect.


Additional information

TxDOT renderings of completed interchange
http://www.transguide.dot.state.tx.us/PublicInfo/xsectimgs.php


This page last updated
March 31, 2008 11:41 AM